Statoil cut steel for Johan Sverdrup drilling platform

Monday, February 15, 2016      
 
  • On Monday 15 February 2016 Haugesund mayor Arne-Christian Mohn started the machine cutting the steel for the Johan Sverdrup drilling platform.

This marks the start of the construction of the Johan Sverdrup drilling platform at Aibel's yard in Haugesund.

'Aibel won the contract for the construction of the drilling platform about one year ago. Following an extensive planning and engineering process it feels good to start the construction of the first of four topside structures for the Johan Sverdrup project', says Kjetel Digre, Statoil's senior vice president for the Johan Sverdrup project.

'More than 14 000 people are involved in the Johan Sverdrup project on a daily basis in 2016, 1000 of them working for Aibel in Norway. We now see the effect of Norwegian industry being competitive, winning most of the principal contracts and equipment deliveries for Johan Sverdrup. We are dependent on all of these people to successfully deliver the project on time, to the required quality, and above all, without any HSE incidents,' Digre says.

The construction contract for the Johan Sverdrup drilling platform was awarded to Aibel in February 2015. The topside engineering work is being performed in Aibel's Asker office, where also Statoil's project team is located.

The 22 500-tonne topsides will consist of three modules, one of which will be built at the yard in Haugesund, one at the Deeline yard in Thailand, and one at Nymo's yard in Grimstad. The modules will be assembled at Aibel's yard in Haugesund in the autumn of 2017, before the platform is installed on the field in 2018.

In the summer of 2015 the pre-drilling templates were installed on the field. The Deepsea Atlantic semi-submersible will start pre-drilling wells on the field in March 2016.

'The most complex platform on the Johan Sverdrup field the drilling platform will come on stream at the end of 2018. We will then start phasing in the pre-drilled wells before production from the field commences at the end of 2019,' Digre says.

The cost development for the Johan Sverdrup project has been positive. So far the investment estimate for the first phase of the development has been reduced by 12 %.

'We are on track in the project, and have seen a positive cost development. This is still in an early stage of the project implementation: What matters now is to maintain focus throughout the process,' Digre concludes.


 

Article Tags

Statoil Norway West Europe


This article is for information and discussion purposes only and does not form a recommendation to invest or otherwise. The value of an investment may fall. The investments referred to in this article may not be suitable for all investors, and if in doubt, an investor should seek advice from a qualified investment adviser. More


Related News


Join 80,000 oil and gas professionals who receive our weekly newsletter.

You may unsubscribe at any time with one click.

Popular Headlines View all


Latest Opinion View all

Join 90,000 other oil and gas professionals

Network with others, build your profile, and receive the latest oil and gas news in your inbox. It's free!

Create profile

Time for a change? All jobs Jobs near you


About

OilVoice, established in 2002, is your leading source of upstream news, jobs and industry information.


Newsletter

Each week we send our weekly industry round-up. Why not try it? You may unsubscribe at any time.

Contact OilVoice

Milton Keynes
United Kingdom
Contact Us


Stay Connected


2016 © OilVoice  .  Privacy Policy  .  Terms of Service  .  Oil Careers  .  Advertise with us