Further to the release dated the 4 January 2012, Enegi is pleased to announce that Schlumberger has mobilised equipment and personnel to the Garden Hill South ('GHS') property and the next stage of the workover has now commenced with flow tests being conducted and chemically conditioned crude being pumped down the PaP#1-ST#3 well.
Photographs of operations at GHS have been posted on the Company website at www.enegioil.com/operations/image-bank. More will be added as the workover progresses.
As well as facilitating preparation for commercial production, the workover is expected to provide further data that will enable the Company to complete the Development Plan for GHS with the objective being to significantly enhance the ultimate recovery of hydrocarbons from the reservoir.
As outlined in the Company's announcement on 21 December 2011 the workover is expected to consist of a number of tasks, including:
- Establishing safe injection rates and pressures, by conducting flow tests and by pumping chemically conditioned crude oil down the well;
- A bullhead acid squeeze on the target formation;
- Shutting-in the well for a soak period;
- Flowing the well to recover treatment chemicals;
- Shutting-in the well until reservoir pressure recovers;
- Flow testing at low rates for a 30 to 35 day period to evaluate reservoir inflow and recharge rates above bubble point;
- Shutting-in the well for an extended build up evaluation test.
Updates on the progress of the workover and testing will follow as the programme continues to be implemented.
Corporate Communications
Enegi is pleased to announce that Chris McGillivray will be working with the Company's corporate communications team. Mr. McGillivray (chris.mcgillivray@enegioil.com) has worked in the financial services industry on the banking side for the past 12 years, with TD Commercial Banking and Canadian Imperial Bank of Commerce Business Banking. As part of our improving corporate communication objectives please see facebook (Enegi Oil PLC) and twitter (@enegioil) links at our website home page www.enegioil.com. The Company will also be updating the photos of operation on a regular basis on the Company website.
Alan Minty, CEO of Enegi Oil Plc., commenting on operations:
"We are delighted that the next stage of the workover has now commenced. The workover represents a significant step as we work towards establishing full field development programmes for GHS and our other Canadian assets. We believe this program will contribute to the demonstration of commerciality of the GHS discovery, which Hunt Oil in 1995 initially flowed at rates of up to 1,742 bopd and 1,528 bopd from two separate intervals. These are exciting times for the Company as we embark on and benefit from activity on our assets."
This article is for information and discussion purposes only and does not form a recommendation
to invest or otherwise. The value of an investment may fall. The investments referred to in this
article may not be suitable for all investors, and if in doubt, an investor should seek advice from
a qualified investment adviser. More
Related Companies