Cougar Energy Update on UCG Pilot Project at Kingaroy in Queensland

Tuesday, April 27, 2010

• Successful initiation of first phase of Kingaroy Pilot Plant gas production
• Production temporarily interrupted by well casing blockage, leading to optimisation of future well design
• Well rehabilitation work in progress, and test phase to be advanced with the immediate drilling and installation of two wells scheduled for later in the year
• Production and testing of syngas (and subsequent ramp up) to re-commence in 4-6 weeks
• Power Station Pre-Feasibility Study continues uninterrupted, with planned stages of construction to be finalised in June.

Cougar Energy Limited provides the following update on the operations at its Underground Coal Gasification (UCG) pilot project at Kingaroy in Queensland. Gas Production On 16 March the production and flaring of syngas using wells P1 and P4 commenced. Effective and rapid ignition, and connection of the wells by reverse combustion linking, were all successfully demonstrated. The product gas was of high quality (calorific value in the range 4.8 and 7.1 MJ/m3), with stable gas composition, temperature, pressure and flow rates, thus confirming the suitability of the coal deposit for application of the UCG technology. Process Well Performance All process wells were installed with multiple casing to handle deep swelling clays in the geological profile. After the successful initial gas production phase, restrictions to air and product gas flows were observed, and the gasification process was temporarily discontinued to allow for well inspection. This revealed blockage to the inner casing of both P1 and P4 caused by thermal expansion, and work is now under way to assess their potential for recovery and future use. This experience has resulted in a modification to the casing design and installation process for future wells. The installation of two new process wells, which were scheduled for later this year, will now be brought forward so that the gas production program for the next 12 months can be continued. Production and testing of gas (and subsequent ramp up) in accordance with this program is expected to re-commence in 4-6 weeks.

Dr Len Walker, Cougar Energy's Managing Director commented: 'Although this is a very short set back in our timing at Kingaroy, it is an opportunity to implement well design changes that will enhance and accelerate our future production capability. We anticipate that the new well design will reduce installation time and cost, significant elements in planning longer-term operations.'

Pre-feasibility Study (PFS) The Company advises that the PFS for the construction of the Kingaroy Power Plant continues uninterrupted with the Board scheduled to take decisions in June on the configuration of the building of Stage 1. Following the receipt of confirmation from the Queensland Government, a first stage of up to 30MW of power generation is now being considered by the Company as part of the pilot trial. Following completion of the PFS, a decision will also be taken on the installation of small scale gas generation plant prior to Stage 1 to provide electricity to the site and to sell excess power into the grid, for which transmission line access is already in place. Senior management continues to work on the optimal funding options for the Power Plant, with investor presentations and preliminary discussions being conducted in Australia, Asia, North America and Europe.

This article is for information and discussion purposes only and does not form a recommendation to invest or otherwise. The value of an investment may fall. The investments referred to in this article may not be suitable for all investors, and if in doubt, an investor should seek advice from a qualified investment adviser. More

Related News

Join 70,000 other oil and gas professionals

Network with others, build your profile, and receive the latest oil and gas news in your inbox. It's free!

Your details are never shared or sold. We hate spam too.

» More Jobs       » Upload a free Job       » Upload your CV

More Europe Jobs

More Global Jobs

Opinion & Commentary

  • Eight pieces of our oil price predicament
    A person might think that oil prices would be fairly stable. Prices would set themselves at a level that would be high enough for the majority of producers, so ...
  • Give us a break...
    I see that Oil & gas UK has been talking again about the need for George Osborne to ‘put his money where his mouth is’ (I paraphrase!) and change the fiscal terms operati ...
  • Why it's different this time
    Is this downturn in oil prices going to be different for investors? I think it might. In fact, I think North American energy companies have a good chance of withstanding th ...

» More Opinion & Commentary         » Write for us             RSS RSS

Oil & Gas Training

Mastering 4D Seismic
Ian Jack, London, 06 Nov 2014

Petroleum Geology of West Africa
Duncan Macgregor, London, 12 Nov 2014

Introduction to Contingency Planning: The value to oil and gas companies in high-risk areas
Mark Theobald, London, 18 Nov 2014

All Upcoming Training


Opinions & Commentary

Oil price, Afren, Aminex, Enteq, Ineos and finally...

by Malcolm Graham-Wood

Read More »