Filter news

57278 articles online
Opinion & Comm.
Keyword

All words
Any words

Added
 

Article Tools

 

AltaGas reports strong second quarter results and increases dividend

Thursday, August 1, 2013
  • Stronger earnings also resulted in stronger cash flows.
  • Normalized net income for the six months ended June 30, 2013 increased to $91.1 million, an 80 percent increase over the same period 2012.
  • For the six months ended June 30, 2013, normalized EBITDA increased 76 percent to $252.1 million compared to $143.1 million for the same period 2012.

AltaGas Ltd. (AltaGas) (TSX:ALA) (TSX:ALA.PR.A) (TSX:ALA.PR.U) today reported a 150 percent increase in normalized net income per share. Normalized net income applicable to common shares was $35.5 million ($0.30 per share) for the three months ended June 30, 2013, compared to $10.4 million ($0.12 per share) for the same period 2012. Net income applicable to common shares reported was $35.9 million ($0.31 per share) for the three months ended June 30, 2013, compared to $25.8 million ($0.29 per share) for the same period 2012.

Stronger earnings also resulted in stronger cash flows. Normalized EBITDA more than doubled to $106.2 million for second quarter 2013 compared to $51.7 million in second quarter 2012. Normalized funds from operations increased to $83.1 million ($0.71 per share) for second quarter 2013 compared to $40.7 million ($0.45 per share) for second quarter 2012.

"We are pleased to report another very solid quarter with substantial growth in earnings and cash flow," said David Cornhill, Chairman and CEO of AltaGas. "We had strong performance from all our businesses and we have attractive growth opportunities. Therefore, we are pleased to announce our Board approved a dividend increase of a quarter cent per share per month. In addition to the increase approved last quarter, this results in a $0.09 cent or 6.25 percent increase to our dividend on an annualized basis. On a full year basis the dividend is now $1.53 per share. The Board and management remain committed to enhancing returns for our shareholders."

Normalized net income for the six months ended June 30, 2013 increased to $91.1 million, an 80 percent increase over the same period 2012. Normalized net income per share increased 46 percent to $0.82 per share, up from $0.56 per share.

For the six months ended June 30, 2013, normalized EBITDA increased 76 percent to $252.1 million compared to $143.1 million for the same period 2012. Normalized funds from operations for the six months ended June 30, 2013, increased 78 percent to $205.5 million ($1.84 per share) compared to $115.5 million ($1.29 per share) for the same period 2012.

Operating income from the business segments increased 89 percent in the second quarter 2013 compared to the same quarter 2012, primarily driven by the addition of the U.S. utilities in August 2012, higher throughput in the Gas business, higher power prices realized and the addition of the new Blythe power facility in mid-May 2013. Earnings were partially offset by lower frac spreads and higher operating costs in the quarter.

AltaGas also announced today that its wholly owned subsidiary Pacific Northern Gas Ltd. (PNG) has entered into Transportation Reservation Agreements with both Douglas Channel Gas Services Ltd. and AltaGas Idemitsu Joint Venture Limited Partnership for 520 Mmcf/d of natural gas transportation capacity on the proposed PNG pipeline expansion. The PNG expansion is expected to increase capacity of the PNG system to approximately 750 Mmcf/d from its current capacity of 115 Mmcf/d. PNG continues to work with other potential shippers for the remaining capacity.

"Securing shippers for the expansion of our PNG pipeline has been a critical milestone toward executing on our LNG export plans," said Mr. Cornhill. "We are pleased with our progress and continue to work with other shippers to secure the remaining capacity on the pipeline expansion. We continue to lead the way in getting Canadian natural gas to export markets."

AltaGas also announced today the expansion of its Cogeneration fleet at Harmattan to 45 MW. AltaGas will construct the new 15 MW Cogeneration facility to meet the increased power demand at the Harmattan complex and increase sales to the Alberta power market. Cogen III is expected to be in service in the fourth quarter 2014 with a total project cost estimated at $40 million.

AltaGas is also expanding its Cold Lake natural gas transmission system to deliver natural gas to provide steam to two heavy oil projects near Cold Lake, Alberta. The estimated cost of both projects is $17 million and both are underpinned by long-term take-or-pay transportation agreements. The expansion is expected to be in service in late 2014.

AltaGas continues to make good progress on the Northwest run-of-river projects, which include the Forrest Kerr, McLymont Creek and Volcano Creek generation facilities. The projects remain ahead of schedule and on budget. The powerhouse activities continue as planned and the power tunnel inlet gate control structure and intake desander structure was completed in the quarter. Three turbine units are on-site with installation expected to begin by mid-August. The installation of the penstock and turbines are expected to be completed in third quarter 2013. The project is expected to be mechanically complete by the end of 2013, with commissioning to follow based on the availability of the Northwest Transmission Line (NTL). In-service date is on target for mid-2014.

Construction continues to progress on both the 66 MW McLymont Creek project and 16 MW Volcano Creek project. The McLymont Creek engineering design is now 95 percent complete. Construction of the 7-kilometre McLymont intake access road is on-going and the pioneer trail is 55 percent completed and anticipated to be completed within the next 90 days. Excavation of the McLymont power portal has been completed and approximately 15 percent of the 2,800-metre power tunnel has been excavated. Excavation of the Volcano Creek intake site and diversion have been completed and the installation of the weir embeds has commenced. At Volcano Creek 100 percent of the penstock right-of-way has been cleared and excavation of the penstock trench has commenced. The powerhouse foundation is approximately 80 percent complete and excavation of the headrace is complete. The two projects are expected to be in service in mid-2015.

This article is for information and discussion purposes only and does not form a recommendation to invest or otherwise. The value of an investment may fall. The investments referred to in this article may not be suitable for all investors, and if in doubt, an investor should seek advice from a qualified investment adviser. More

Related Companies

Related News

Join 70,000 other oil and gas professionals

Network with others, build your profile, and receive the latest oil and gas news in your inbox. It's free!

Your details are never shared or sold. We hate spam too.

Key Supporters


 

» More Jobs       » Upload a free Job       » Upload your CV

More Europe Jobs

More Global Jobs

Opinion & Commentary

  • Are oil and gas companies capable?
    Investors, at least those in the UK, are deeply disillusioned with the oil & gas sector, not because they think the oil price is going to drop any time soon, nor beca ...

» More Opinion & Commentary         » Write for us             RSS RSS

OilVoice Magazine
Oil Echo
Oil Earth

Opinions & Commentary

Tech Talk - Here we go again, again

by David Summers

Read More »