ATP Announces Deepwater Development Update
Friday, March 12, 2010
ATP Oil & Gas Corporation announces that its major deepwater Gulf of Mexico development, the Telemark Hub, is on schedule for first production later this month. At ATP's other deepwater development, the Canyon Express Hub, the MC 217 #3 well was placed on initial production March 11, 2010 at 30 MMcf/d gross.
Telemark Hub Update
ATP's major deepwater Gulf of Mexico development, the Telemark Hub, is on schedule to commence production during March 2010 from the Atwater Valley 63 # 4 well. This well was tested in February at a gross rate in excess of 10,700 Boe/d from two zones. The ATP Titan, the Telemark Hub's state-of-the-art floating production and processing facility, is in the final stages of commissioning following the installation of all major production and processing components. The sales pipelines have been hydro-tested and dewatered.
The initial sections of the Nabor's platform rig 202 began arriving this week. Following erection of the drilling rig on the ATP Titan over the next several weeks, ATP will begin the process of re-entering and completing the Mississippi Canyon ("MC") 941 #3 well. The MC 941 #3 well, which has been drilled and cased, is expected to commence production in the second quarter 2010. In September 2009, this well encountered 266' of net pay, triple the amount of net pay found in the original control well.
ATP operates the Telemark Hub with a 100% working interest and owns 100% of the ATP Titan and associated pipelines and infrastructure.
Canyon Express Hub Update
At King's Peak, the MC 217 #3 well began production through the Canyon Express pipeline on March 11, 2010 at a gross rate of 30 MMcf/d. At Aconcagua, MC 305, two additional wells, the #3 and #4, are scheduled to resume production at a rate of 30 MMcf/d gross, bringing the entire Canyon Express Hub production rate up to 60 MMcf/d gross.
ATP operates the Canyon Express Hub with a greater than 50% working interest in the wells and associated pipelines, which have a throughput capacity of approximately 500 MMcf/d.
View our focused
Gulf of Mexico
link and stay in touch with the latest news and companies active in this region
©
OilVoice -
http://www.oilvoice.com/n/ATP Announces Deepwater Development Update/4323fda0d.aspx